Our role and approach
Solid Port Solutions delivered the overall project management and support to ensure on-time and within budget delivery of the entire project. This was all done with support from Lineage staff and Lineage site management.
As the project contained almost all aspects of building a new terminal the decision was made to divide the investment into seperate phases that could be handled in parallel by different teams of different disciplines.
1) Selection and implementation of a new Terminal Operating System
- Writing both functional and technical specifications
- Managing the procurement and vendor selection
- Support on implemenation, integration and configuration
- Support on testing software and reporting user errors
- User training
- Go-Live support
2) Empty depot and new fully automated entrance
- Support on civil design of both Empty Depot and automated entrance
- Functional description for the Empty Depot entrance
- Testing the new gate and new software functionalities
- Go-Live support
3) Selection and Implementation of Auto-RTG stacking cranes
- Writing both functional and technical specifications
- Writing equipment control requirements
- Managing the procurement and vendor selection
- Support on implemenation and operational integration
- Support on testing and reporting user errors
- Go-Live support
- Independent project engineer between the vendor and the customer for issue resolvement